# Fee Quote: Ceramics Garden Studio in Roundhay, Leeds

## Fee quote

### Fee quote for a new garden studio in Roundhay

*Fee quote · Ginnel Architects, Leeds*

A fixed fee of £18,837 plus VAT to design, win consent for and see built a 42 m² ceramics studio at the end of your garden. Valid until Friday 19 February 2027.

- Prepared for: Rhiannon Ridgeway and Kofi Mensah
- Issued: 18 January 2027
- Reference: Q-2027-014

*A dark timber garden studio at the end of a lawn*

*Ginnel Architects*

## The job

### The job as we understand it

*The job*

You need a working ceramics studio at home before the lease on your shared workshop in Holbeck ends on 31 December 2027.

After our visit on Tuesday 12 January, this is what we are pricing: a single-storey studio of 42 m² at the north end of the garden, with a throwing room, a separate kiln room on its own electrical supply, glaze storage and a sink. Cross-laminated timber on screw piles, so the two beech trees keep their roots.

It stands within two metres of the boundary and rises above 2.5 metres, so it needs a householder planning application. That wait shapes the programme more than the design does. If any of this is wrong, tell us before you read the fee.

## Who is quoting

Ginnel Architects is five people in Leeds, founded in 2017. We design small new buildings and little else. Imran Whitaker, director, leads your project. Bryony Stead, project architect, draws it and inspects it on site.

### Weaving studio, Ilkley

*Timber weaving studio interior under a rooflight*

### Print room, Meanwood

*Larch-clad garden building on a sloping plot*

### Music room, Otley

*Oak-lined music room with an upright piano*

## Scope

### What the fee covers

The work follows the RIBA Plan of Work, Stages 1 to 6. Each stage ends with something you can hold us to.

### 1. Stage 1: Brief and appraisal

Two weeks. A written brief, a site appraisal with the tree survey read into it, and a cost check against your £144,900 build budget.

### 2. Stage 2: Concept design

Four weeks. Two layouts in a shared 3D model you can walk through in a browser, then one developed option with an outline specification.

### 3. Stage 3: Planning application

Four weeks to coordinate the design and prepare the drawings. We then submit the householder application and manage it through the eight-week determination.

### 4. Stage 4: Technical design

Six weeks. Construction drawings, specification and the Building Regulations submission, followed by a four-week tender to two contractors and a tender report.

### 5. Stage 5: Construction

Ten weeks on site. We administer a JCT Minor Works contract, inspect fortnightly, certify payments and answer the contractor's queries within two working days.

### 6. Stage 6: Handover

One week. Snagging inspection, practical completion certificate, and a handover file with the as-built model, warranties and the kiln room commissioning record.

## The principle

A small building still needs every stage. It does not need a fee that moves, so ours is fixed at 13 percent.

## The fee

All figures in GBP, excluding VAT. The fee is 13 percent of a £144,900 construction budget (42 m² at £3,450 per m²), fixed at £18,837 and split by stage. It does not rise if tenders come in higher.

#### Fixed fee, RIBA Stages 1 to 6

| Item | Price |
| --- | --- |
| Stage 1, brief and appraisal | $1,884.00 |
| Stage 2, concept design | $3,767.00 |
| Stage 3, planning application | $3,767.00 |
| Stage 4, technical design and tender | $4,710.00 |
| Stage 5, contract administration | $3,767.00 |
| Stage 6, handover | $942.00 |

#### Optional extras

| Item | Price |
| --- | --- |
| VR walkthrough at Stage 2 | $680.00 |
| Passivhaus-level energy model | $1,450.00 |
| Planting plan around the studio | $1,240.00 |
| Fitted workbench and storage wall | $1,860.00 |

- VAT: 20%

## Programme

Forty-two weeks from a start on Monday 1 March 2027 to handover on Friday 17 December 2027, two weeks before your lease ends. It assumes your comments arrive within three working days at each stage.

| Task | Start | End | Duration | Label |
| --- | --- | --- | --- | --- |
| Brief and site appraisal | 2027-03-01 | 2027-03-12 | 5 days | Design |
| Concept design in the shared model | 2027-03-15 | 2027-04-09 | 5 days | Design |
| Coordination and planning drawings | 2027-04-13 | 2027-05-07 | 5 days | Planning |
| Householder application submitted | 2027-05-10 | 2027-05-11 | 5 days | Planning |
| Planning determination | 2027-05-11 | 2027-07-05 | 5 days | Planning |
| Technical design and Building Regulations | 2027-07-12 | 2027-08-20 | 5 days | Technical |
| Tender to two contractors | 2027-08-23 | 2027-09-17 | 5 days | Technical |
| Construction on site | 2027-10-04 | 2027-12-10 | 5 days | Site |
| Snagging and handover | 2027-12-13 | 2027-12-17 | 5 days | Site |

## Exclusions and terms

### What is not in this fee

Written down now, so nothing arrives later as a surprise.

### Costs you pay directly

The planning fee, Building Control fees, the topographical and tree surveys, and any party wall surveyor. We expect these to total about £2,900 and will confirm each one before it is ordered.

You pay the supplier directly, so there is no margin on them.

### Other consultants

A structural engineer for the screw piles and timber frame, and an electrical designer for the kiln supply. Both are separate appointments, made by you on our recommendation.

Allow £3,400 for the two. Coordinating their work is part of our fee.

### Planning risk

No architect can promise consent, and we do not. 29 of our 31 householder applications have been approved at the first attempt.

If yours is refused, one revised submission is included. An appeal is not, and would be quoted separately.

### Changes after approval

Each stage includes two rounds of comments. Changing an approved design after Stage 3 is charged at hourly rates: director £165, architect £110.

We give you the hours in writing before we start any of it.

### Validity and what moves the dates

This quote holds until Friday 19 February 2027. After that we would need to check that the 1 March start is still free.

Late comments move every date after them by the same amount. With two weeks of float before your lease ends, that matters.

### Appointment basis

On acceptance we issue the RIBA Domestic Professional Services Contract, with this quote attached as the schedule of services and fees.

We act as principal designer under CDM 2015 and under the Building Regulations at no extra charge.

## Clients

### Three clients with small buildings

> The fee on the quote was the fee on the last invoice, to the pound. When the tenders came in £6,000 over, they redrew the roof in a week and got the price back down without losing the rooflight.

— Greta Holroyd, Founder, Holroyd Weave

> They told us in the first meeting that planning would take longer than the design, and they were right. The application went in on the date in the programme and consent arrived nine days early.

— Samir Qureshi, Director, Northlight Print Club

> Bryony was on site every fortnight with a list. She caught a door set fitted without its acoustic seal before the plasterboard went on, which saved us reopening a finished wall.

— Leona Bassey, Founder, Low Register Studios

## Accept

### Accept by 19 February to hold the March start

Confirm below and Imran will send the appointment contract the same day. Stage 1 begins on Monday 1 March 2027 with a half-day at the house.

### Prepared by

**Imran Whitaker**
Director, Ginnel Architects

Unit 4, Canal Wharf Yard
Leeds LS11 5PS
imran@ginnelarchitects.co.uk

### For approval by

**Rhiannon Ridgeway and Kofi Mensah**
Roundhay, Leeds LS8

If you would rather talk it through first, Imran has held Thursday 28 January at 5.30 pm, at the house or by video.

### Accept this quote

By confirming, you accept the scope, programme and fixed fee above: £18,837 excluding VAT across RIBA Stages 1 to 6, plus any extras you have ticked, starting Monday 1 March 2027. We will send the RIBA contract for signature and invoice Stage 1 when the brief is issued.