# Fee Variation 02: Two Rooms Added to Baakenallee 41

## Fee variation 02

### Fee variation 02: two rooms added to scope

A home office and a guest suite, requested on 6 April 2027 after concept approval. This document prices the change and states its effect on fee, furniture budget and programme.

- Prepared for: Jorinde and Malte Steenbock
- Issued: 13 April 2027
- Decision by: 23 April 2027

*Empty new-build room at dusk with a tall window and oak floor*

*Brodersen Thiele Interior mark*

## What changed

### What changed and who asked

*The change*

At the design meeting on 6 April 2027 you asked us to bring rooms 6 and 7 into the scope: room 6 as a home office, room 7 and its shower room as a guest suite.

Our agreement of 18 January 2027 covers five rooms, 141.2 m² of the 186 m² apartment at Baakenallee 41. Rooms 6 and 7 were to stay as painted shell. You confirmed the request by email on 8 April with two requirements: the office has to carry three days of video calls a week from September, and the guest suite has to suit stays of several months.

The concept you approved on 19 March does not include these rooms, so this is additional work, not a revision. It adds 33.8 m², one run of bespoke joinery with a 10-week lead time, and 31 furniture and lighting items. If we have read the request wrongly, tell us before you read the figures.

## Effect on fee, budget and programme

### The effect in four figures

All amounts are net, in EUR, before 19% VAT. Each figure is the difference against the agreement of 18 January 2027.

### Design fee, net

**+€17,903**

From €61,400 to €79,303. The hourly basis and the rates do not change: €135 senior, €95 designer.

### Furniture budget, net

**+€42,240**

From €184,000 to €226,240. That is €38,400 of goods plus 10% contingency, paid to suppliers at cost.

### Final handover

**+3 weeks**

From 1 October to 22 October 2027. The five approved rooms are still installed by 1 October.

### Added to scope

**33.8 m²**

Room 6 at 11.4 m², room 7 at 17.6 m² and shower room 7a at 4.8 m².

## The added rooms

### Room 6, home office

*Home office with an oak desk wall and a slate blue acoustic panel*

### Room 7, guest bedroom

*Guest bedroom with an oak wardrobe run and a chair at the window*

### Room 7a, shower room

*Compact shower room with pale grey tiles and an oak niche shelf*

## The change, priced

### The change, line by line

All figures in EUR, net of 19% VAT, at the rates in our agreement: €135 an hour senior designer, €95 designer. The furniture budget is not a fee. Suppliers are paid at cost, and it appears here only as the basis of the procurement line.

#### Variation 02, design fee

| Item | Price |
| --- | --- |
| Space planning and concept | $3,240.00 |
| Developed design and joinery drawings | $4,725.00 |
| Lighting and electrical plan revision | $1,215.00 |
| Acoustic design, room 6 | $1,080.00 |
| Specification and FF&E schedule | $2,090.00 |
| Procurement management | $4,608.00 |
| Project coordination | $945.00 |

#### Optional items

| Item | Price |
| --- | --- |
| VR walkthrough of both rooms | $1,350.00 |
| Fold-away second bed, room 7 | $1,890.00 |

- VAT: 19%

## Revised programme

The five approved rooms keep their install dates. Rooms 6 and 7 follow, set by the joinery workshop's next production slot on 19 July and its 10-week lead time. Assumes one consolidated round of comments within five working days.

| Task | Start | End | Duration | Label |
| --- | --- | --- | --- | --- |
| Decision on this variation | 2027-04-19 | 2027-04-23 | 5 days | Design |
| Space planning and concept, rooms 6 and 7 | 2027-04-26 | 2027-05-14 | 5 days | Design |
| Your review of the concept | 2027-05-17 | 2027-05-21 | 5 days | Design |
| Developed design and joinery drawings | 2027-05-24 | 2027-06-11 | 5 days | Design |
| Specification and order sign-off | 2027-06-14 | 2027-06-25 | 5 days | Design |
| Upholstery and loose furniture, 12 weeks | 2027-06-28 | 2027-09-17 | 5 days | Procurement |
| Bespoke joinery, 10 weeks | 2027-07-19 | 2027-09-24 | 5 days | Procurement |
| Install, five approved rooms | 2027-09-20 | 2027-10-01 | 5 days | Installation |
| Install, rooms 6, 7 and 7a | 2027-10-04 | 2027-10-15 | 5 days | Installation |
| Styling, snagging and handover | 2027-10-18 | 2027-10-22 | 5 days | Installation |

## What stays as agreed

The five rooms you approved on 19 March do not change. Their design, fee, budget and install date of 1 October stay exactly as agreed.

## What stays, and the option of no change

### What stays as agreed, and the option of no change

Six points, written down now so that nobody has to remember them in October.

### The five approved rooms

Living and kitchen, main bedroom, both children's rooms and the entrance hall stay as approved on 19 March 2027. No drawing, finish or furniture item in those rooms is reopened by this variation.

Orders already placed for them, €96,750 to date, are not affected.

### If you decide not to make the change

Nothing changes and nothing is owed. The 6.5 hours spent preparing this variation are not charged.

Rooms 6 and 7 stay as painted shell, handover stays on 1 October 2027, and you can commission them later as a separate project. Later means a second install visit and the workshop's lead time at that date, which we cannot hold for you now.

### Fee basis, rates and payment terms

The agreed fee of €61,400 stands. Variation 02 is invoiced separately in three parts: 40% on signature, 40% at order sign-off on 25 June, 20% at handover.

Payment is due 14 days from invoice, as before.

### Furniture budget for the approved rooms

The €184,000 budget and its 10% contingency are ring-fenced. The €42,240 for rooms 6 and 7 runs as a separate cost centre on the live FF&E tracker.

An overspend in one cannot be absorbed by the other without your written approval.

### If the decision comes after 23 April

Each week of delay moves the design stages by a week. The joinery slot of 19 July holds until 7 May.

After that the next slot is 16 August, and handover of rooms 6 and 7 moves to 19 November 2027. The five approved rooms are unaffected either way.

### Assumptions and exclusions

Priced on the developer's as-built drawings of 2 March 2027. Excluded: changes to walls, plumbing or the ventilation system, the electrician's installation cost for the six circuits, and decoration by the main contractor.

Deposits on bespoke items are not refundable once an order is placed. We keep the right to photograph the finished rooms.

## After you sign

Five dates between your signature and handover. Each has an owner, and none of them touches the five approved rooms.

### 1. Sign by 23 April

Your signature releases the first invoice, 40% of the variation, and books the hours. Wiebke Brodersen stays your lead for all seven rooms.

### 2. Concept on 14 May

Layouts, 3D views and materials for rooms 6 and 7, presented at the studio. You have until 21 May for one consolidated round of comments.

### 3. Drawings on 11 June

Joinery drawings go to Elbkant Tischlerei for a fixed price. Lighting and electrical revisions go to your electrician the same day.

### 4. Orders signed off by 25 June

Every item sits on the live FF&E tracker with its price and lead time. Nothing is ordered until you approve it there.

### 5. Handover on 22 October

Rooms 6, 7 and 7a installed, styled and snagged. The five approved rooms are handed over on 1 October as planned.

## Decision and signature

### The decision we need by 23 April

Your signature approves Variation 02: €17,903 net added to the design fee plus any optional items ticked above, €42,240 net added to the furniture budget, and final handover on 22 October 2027. To leave rooms 6 and 7 as they are, do not sign. Reply to Wiebke instead, and the agreed scope, fee and 1 October handover continue unchanged.

### Prepared by

**Wiebke Brodersen**
Partner, Brodersen Thiele Interior

Bernstorffstraße 118
22767 Hamburg
wiebke@brodersenthiele.de

### For approval by

**Jorinde Steenbock or Malte Steenbock**
Clients, Wohnung 5.02

Baakenallee 41
20457 Hamburg

Questions before signing go to Wiebke. She has held Tuesday 20 April at 17:00 for a call.

### Approve fee variation 02

By signing, you approve Variation 02 to the agreement of 18 January 2027: an additional design fee of €17,903 net plus any optional items ticked above, a furniture budget increase of €42,240 net, and final handover on 22 October 2027. We will invoice 40% of the variation on signature.